Environmental Site Assessment Process

Interactive guide from Phase I records review through remediation to regulatory closure

Where Am I in the Process?

Typical Timeline Overview

Phase I
4-8 wks
$3K-15K
Phase II
6-12 wks
$15K-100K+
Phase III
3 months - 5+ years
$50K-millions
Closure
1-6 months
$5K-25K
I
Phase I ESA

Records Review

Identify potential contamination through non-invasive investigation

4-8 weeks $3K-15K
Process Steps
  1. 1 Records review - historical land use, environmental databases, regulatory files
  2. 2 Site reconnaissance - visual inspection, photographic documentation
  3. 3 Interviews - current and past owners, occupants, local officials
  4. 4 Report - findings, RECs, CRECs, HRECs with conclusions
Standards by Jurisdiction
🇺🇸 ASTM E1527-21
🇨🇦 CSA Z768
🇬🇧 BS 10175
🇦🇺 AS 4482.1
Duration & Cost

4-8 weeks typical turnaround
$3,000 - $15,000
Cost varies with property size, complexity and jurisdiction

When Required

Property purchase or sale
Refinancing or loan applications
Land use change or rezoning
Environmental due diligence
Regulatory compliance review

Key Terminology

REC (Recognized Environmental Condition) - indicates likely contamination requiring further investigation. CREC (Controlled REC) - past contamination addressed with controls in place. HREC (Historical REC) - past contamination that has been fully remediated with no remaining concern.

II
Process Steps
  1. 1 Sampling plan design based on Phase I findings
  2. 2 Soil sampling - test pits, boreholes, hand augers
  3. 3 Groundwater sampling - monitoring well installation and sampling
  4. 4 Laboratory analysis of collected samples
  5. 5 Risk assessment and comparison to regulatory standards
  6. 6 Report with conclusions and recommendations
Standards by Jurisdiction
🇺🇸 ASTM E1903
🇨🇦 CSA Z769
🇬🇧 BS 10175
🇦🇺 AS 4482.2
Duration & Cost

6-12 weeks typical turnaround
$15,000 - $100,000+
Cost depends on number of samples, depth of investigation and contaminants of concern

Key Decisions

Delineation extent - how far to sample
Parameters to test - metals, hydrocarbons, VOCs, etc.
Number and depth of samples
Need for monitoring wells
Applicable regulatory thresholds

What Happens Next

If results are below regulatory thresholds - no further action required. The site is considered clean. If results exceed thresholds - remediation (Phase III) is required. Additional delineation sampling may be needed first to define the full extent of contamination.

III
Process Steps
  1. 1 Develop remediation plan - approach, timeline, cost estimate
  2. 2 Obtain regulatory approval for the remediation strategy
  3. 3 Implementation - excavation, treatment, containment or monitoring
  4. 4 Confirmation sampling to verify cleanup targets are met
  5. 5 Closure report documenting all remediation activities
Common Remediation Methods

Excavation and disposal - dig and haul contaminated soil
Soil vapor extraction - remove volatile contaminants
Bioremediation - use microorganisms to break down pollutants
Pump and treat - extract and treat contaminated groundwater
Risk management - institutional controls, barriers, monitoring

Duration & Cost

3 months to 5+ years depending on approach
$50,000 to millions
Timeline and cost vary dramatically based on contamination type, volume, depth and chosen remediation approach

Estimate Your Costs

Use our cost estimator to get a preliminary budget range for your remediation project.

Open Cost Estimator Tool
Process Steps
  1. 1 Compile final reporting package with all investigation and remediation data
  2. 2 Submit closure application to the relevant regulatory authority
  3. 3 Regulatory review and any follow-up requests
  4. 4 Certificate of Compliance or equivalent closure document issued
Jurisdictional Notes
  • BC, Canada - Certificate of Compliance (CoC) under the Environmental Management Act
  • Ontario, Canada - Record of Site Condition (RSC) filed in the Environmental Site Registry
  • United States - No Further Action (NFA) letter from state environmental agency
  • United Kingdom - Part 2A determination or voluntary remediation statement
Important Considerations

Closure documents are land-use specific. A site closed for commercial use may need additional work if converted to residential. Some jurisdictions allow risk-based closure with ongoing monitoring requirements rather than full cleanup to background levels. Closure timelines depend heavily on the regulatory backlog in your jurisdiction.

This guide is for general educational purposes. Actual ESA requirements vary by jurisdiction, property type and regulatory context. Always consult a qualified environmental professional and your local regulatory authority for site-specific guidance.

Track Your ESA Project

Log site assessments, track phases, manage documents and generate compliance reports with EnviroLog.

Try EnviroLog Demo